Source: Yiwu sourcing agent Author: Helan Date: 2008-07-19
At 10:00 on July 16, Wing CMG Steel Co. electric furnace production workshop three groups to stop running. The day is Bifeng electricity enterprises, the first day. In order to cope with peak summer electricity consumption, giving priority to ensure that residents living electricity, Yongkang some enterprises to adjust production schedule, and consciously avoid the peak electricity grid.
At 10:25 on July 16, Wing Hong grid electricity load has grown, and the highest negative Heda 403,800 kilowatts, of electricity for the whole situation is quite grim. Network equipment in order to ensure the safe operation of the main, Yongkang City in an orderly manner electricity requirements of the Office of the daily 7:30 to 11:00 and 12:30 to 16:00 two sessions, Yongkang economic development zone, Chi-ying, Fang Yan, Yongsan , Xixi, the ancient mountain, the stone columns, and other industrial enterprises must take the wrong Bifeng,Adjust production time, by the early work and delay the work, such as arrangements for low production period, to avoid morning and evening peak periods of two electricity, the use of low power.
At present, Yongkang power grid during peak load 380,000 kilowatts to 400,000 kilowatts, low hours (22:00 to 8:00 the next day) load 190,000 kilowatts to 20 kilowatts of electricity shortfall amounted to a peak times, low hours of electricity load Rate to be substantially increased.
Prev:Yiwu tie hard to copy"Shengzhou sample" Next:A promising future awaits Yiwu's exhibition industry