Yesterday, reporters in the provincial key projects Yiwu inland ports station construction site that is responsible for the station's remaining within the bending road construction engineers with engineering and technical personnel, on the newly completed bridge closure of the winding mountain path carefully check the main project. According to reports, the station bridge the winding mountain path length 1,200 meters, with A, B, C, D, E 5 ramp. Currently winding mountain path have been closing the bridge, approach bridge and the green being next ancillary construction. It is reported that the inland port of the station has been completed for 78% of the total project amount is expected to be completed and delivered at the end.